More works being done over the week!
Really hope we can get our approval for the hacking works upstairs for the French windows.
Really hope we can get our approval for the hacking works upstairs for the French windows.
balcony fully plastered. Ready for tiling works |
zoom in on balcony plaster |
other wall of balcony end |
Master bath - tiling works 70% completed. |
Common bath entrance area |
Common bath - shower area tiled leaving alcove area |
Panoramic view of dining and kitchen |
Timber frames delivered to site |
Future Pantry area |
Master bathroom - all walls are tiled |
Master bathroom - waiting for alcove wall to up before final tiling works |
Yard wall up! |
Panoramic view of kitchen |
Powder room - area to be hacked |
Powder room, wall fully tiled |